91. Final technical authority of a project lies with
92. A Milestone chart
93. Pick up incorrect statement from following:
94. If total float and duration of an activity are 5 and 10 days respectively, particular activity can be
95. If t is duration of an activity, t1 is latest finish possible moment of its preceding activity and t2 is earliest start possible moment, independent float of activity is
96. A construction estimate is used
97. In measurement of masonry activity, no deduction is made for ______.
98. Which of following statements is/are correct with respect to methods of valuation?
i) In Rental method of valuation, net income by way of rent is found out by deducting all outgoings from gross rent.
ii) In Development method of valuation, building should be divided into four parts i.e. Walls, roofs, floor and doors, windows.
99. What is unit of payment in MKS system for Earthwork in banking, cutting in road and irrigation channel?
100. Which of following areas is NOT included in plinth area?
All Chapters
Topics
Civil engineer 7th level loksewa exam important questions
Final technical authority of a project lies with
A Milestone chart
Pick up incorrect statement from following:
If total float and duration of an activity are 5 and 10 days respectively, particular activity can be
If t is duration of an activity, t1 is latest finish possible moment of its preceding activity and t2 is earliest start possible moment, independent float of activity is
A construction estimate is used
In measurement of masonry activity, no deduction is made for ______.
Which of following statements is/are correct with respect to methods of valuation?
i) In Rental method of valuation, net income by way of rent is found out by deducting all outgoings from gross rent.
ii) In Development method of valuation, building should be divided into four parts i.e. Walls, roofs, floor and doors, windows.
What is unit of payment in MKS system for Earthwork in banking, cutting in road and irrigation channel?
Which of following areas is NOT included in plinth area?