- Permissible error in a single horizontal distance should be within 1 in 500, and vertical distance should not exceed 0.1m.
- In open traverse, average error should not exceed 1 in 600 to 1 in 850.
- For sights upto 120m, an accuracy of `1/3000` to `1/10000` is must.
- Closing error in stadia traverse > `0.055 root(P)`, `P` is the perimeter of the traverse.
- Error in closing for elevation varies from `0.08 root(K)` on level ground to `0.25 root(K)` on hilly ground, where `K=` distance in km.
All Chapters
View all Chapter and number of question available From each chapter from Surveying-II
Traversing
This is the detailed course containing all past IOE exam solution chapterwise plus important theory..
Tacheometry Surveying
This is the detailed course containing all past IOE exam solution chapterwise plus important theory..
Trignometric Levelling
Geographic Information System
Total Station
Field Astronomy and GPS
Similar Question
This Chapter Tacheometry-Surveying- consists of the following topics
Guest