MCQ
A contractor agreed to build 30 temporary sheds in 90 days at a price of Rs. 10000/unit. Twenty days later, the contract…
From Construction Management mcqs · Construction Management
A contractor agreed to build 30 temporary sheds in 90 days at a price of Rs. 10000/unit. Twenty days later, the contract…
Pick up the incorrect statement from the following:
Economic saving of time results by crashing
PERT analysis is based on
Mobilization advance up to 10% of the cost of work is given to a contractor
For a given size of bucket, the ideal output of a dragline will be least in
Completion of an activity on CPM network diagram, is generally known
The technique for establishing and maintaining priorities among the various jobs of a project, is known