Bar charts are suitable for
The figure below shows the network for a particular project which consists of four activities.

|
Activity |
Normal time (days) |
Crash time (days) |
|
1-2 |
3 |
2 |
|
2-3 |
4 |
2 |
|
2-4 |
5 |
4 |
|
3-4 |
7 |
5 |
The minimum time required for the completion of the project is _________
All Chapters — Construction Management
Similar Questions
From Construction Management mcqs · Construction Management
MCQ
MCQ
Sinking fund is
MCQ
Frederick W. Taylor introduced a system of working known as
MCQ
The main advantage of line organisation, is :
MCQ
A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital re…
MCQ
PERT technique of network analysis is mainly useful for
MCQ
During the construction period, price variation clause in contracts caters to
MCQ
Mobilization advance up to 10% of the cost of work is given to a contractor