Construction-Management-mcqs
The figure below shows network for a particular project which consists of four activities.

Activity
Normal time (days)
Crash time (days)
1-2
3
2
2-3
4
2
2-4
5
4
3-4
7
5
The minimum time required for completion of project is _________
The figure below shows network for a particular project which consists of four activities.

|
Activity |
Normal time (days) |
Crash time (days) |
|
1-2 |
3 |
2 |
|
2-3 |
4 |
2 |
|
2-4 |
5 |
4 |
|
3-4 |
7 |
5 |
The minimum time required for completion of project is _________
All Chapters
View all Chapter and number of question available From each chapter from Construction-Management
Similar Question
This Chapter Construction-Management-mcqs consists of the following topics
A contractor agreed to build 30 temporary sheds in 90 days at a price of Rs. 10000/unit. Twenty days later, the contractor has finished 8 sheds with an actual total cost of<br> Rs. 85000. What is the status of the project?</p>
The figure below shows network for a particular project which consists of four activities.

|
Activity |
Normal time (days) |
Crash time (days) |
|
1-2 |
3 |
2 |
|
2-3 |
4 |
2 |
|
2-4 |
5 |
4 |
|
3-4 |
7 |
5 |
The minimum time required for completion of project is _________