Fulkerson’s rule is used for numbering the
From Construction Management Loksewa Mcqs · Construction Management
Fulkerson’s rule is used for numbering the
A dummy activity
If the path of activities leads back into itself, the resulting error in the network is known as
The time by which the completion of an activity can be delayed without affecting the start of succeeding activities is c…
In PERT analysis, the time estimates of I activities and probability of their occurrence follow
Critical path
Positive float for any activity means that the activity is
which would represent the pessimistic time estimate.