You may be aware that the GoN planned to construct two dams near the source of Bagmati River. Dhap dam, the first of the two is already constructed and Nagamati is under preparation. Dhap dam is designed to discharge 40 lps water with BOD5 of 5 mg/L to Bagmati River and Nagamati is designed to discharge 400 lps water to Bagmati River with BOD5of 8 mg/L. Both dams will be operated during 8 months of the dry period. Both dams will discharge at upstream of the river, which then passes through Gokarna, Guheshwori and Pashupati. Guheshwori has a new waste water treatment plant, which is in operation now. Guheshwori WWTP which is in operation, discharges 370 lps treated waste water with a BOD5of 10 mg/L.  Now, calculate the BOD5 of Bagmati River at Pashupati assuming Nagamati dam is also operational and there are no other sources that contribute water or waste water in the Bagmati other than these three sources. Your calculation is for the 8 months when dams are releasing water into the Bagmati.

[2079-10-14 Sangh] [5]


Previous Question Next Question
🔗

Similar Questions

From Sanitary engineering · Civil engineering 7th level second paper question bank

View All
WhatsApp