Write the name of six hydropower project which are in operation with their installed capacity. A run-off river plant is installed on a river having a minimum flow of 15 m³/ sec. If the plant is used as a peak load plant operating only for 6 hours daily, compute the firm capacity of the plant: a) without pondage; b) with pondage but allowing 8% water to be lost in evaporation and other losses. Head at the plant is 16 m, and the plant efficiency may be assumed as 80%.

[2080-10-04 Gandaki] [10]