A site investigation has to be done for a 6-lane bridge to be constructed in Karnali river. The client seeks the information on bearing capacity and settlement of foundation for the bridge. What method of site investigation and in-situ tests would you advise as a project engineer? Explain the in-situ test you advised in detail.