| 1. Calculate number of bags of cement required for 12 mm thick plastering of a wall of 5 m long, 3.5 m high and 300 mm thick, if 1: 3 cement mortar is used. |
| 3. Pick up correct statement from following: |
| 4. For fourth class building doors and windows shall be of ...................wood or country wood. |
| 5. The area of a sloping surface of a protective embankment of mean height ‘d’, side slopes S : 1 and length ‘L’ is |
| 6. Size, capacity and materials need be specified for |
| 7. The measurement is made for stone work in square metre in case of |
| 8. What is quantity of cement (in kg) and of dry sand (in cubic meter) respectively required for preparing 1 cubic meter of wet cement mortar of 1 : 5 proportion? |
| 9. Berms are provided in canals if se are |
|
10. In mid-section formula
|