Chapter:

engineering-professional-practice-part-3

1. The purpose of bid evaluation is to determine


2. If registration of an engineers is canceled from NEC his name will be registered or not if engineer is ready to register his name (sec-18 NEC regulation


3. Engineering shall act in such a manner as to uphold and enhance honor and dignity of engineering profession and shall act with ......... for bribery, fraud and corruption.


4. According to labour act considering health condition is


5. Fundamental principle of Professional Engineering Ethics is:


6. The user\'s committee method of construction is labour intensive with a cost estimate upto (Source:PPR 2064(97)):


7. The minimum and maximum no. of members on user\'s committee should be


8. As per prevailing Public Procurement Acts & Regulations of Nepal, provision of price adjustments is normally to inculpated in civil works contract having project duration ?


9. To work for survey, design estimate & supervision of a road project, consultant has to submit


10. According to Public Procurement Regulation, 2064, Who approves prequalification criteria ?