MCQ
Pick up the incorrect statement from the following:
From Estimating And Costing Mcqs · Estimating And Costing Mcqs
Pick up the incorrect statement from the following:
For 100 sq. m cement concrete (1 : 2 : 4) 4 cm thick floor, the quantity of cement required, is
Pick up the correct statement from the following:
The brick work is not measured in cu m in case of
Which of the following states that work expands to fill the time available.
The concrete work for the following part of the building of specified thickness is measured in square metres
It is often difficult to estimate size at an early stage in a project when only a specification is available
According to ISI method of measurement, the order of the sequence is