Highway Drainage
Course: Highway Engineering — Practice MCQs, solutions, formulas & past entrance questions.
Chapter:
highway-drainage (Click to view content)
|
1. The rural roads are provided with ______ |
|
2. The structure provided on pavement to remove storm water is _______ |
|
3. For a bitumen pavement calculate discharge in m3/sec if intensity of rainfall is 40 mm/sec and area of drainage is 100 m2. |
|
4. If depth of a trapezoidal section is 0.50 m and free board is 0.15 m, n total depth is? |
|
5. If canal and drain at same level n cross drainage structure is called ______ |
|
6. The number of steps followed for surface drainage system is ______ |
|
7. The desirable velocity for sand and silt are ______ |
|
8. The increase in moisture causes strength to ______ |
|
9. The GWT should be at a distance of ___ from ground level. |
|
10. The highway drainage system consists of how many types? |
All Chapters
View all Chapter and number of question available From each chapter from highway-engineering
Highway Engineering Basics
Highway Engineering Basics
Highway Development and Planning
Highway Development and Planning
Highway Alignment and Project Preparation
Highway Alignment and Project Preparation
Geometric Design of Highways
Geometric Design of Highways
Traffic Engineering
Traffic Engineering
Properties of Highway Materials
Properties of Highway Materials
Design of Highway Pavements
Design of Highway Pavements
Highway Construction
Highway Construction
Soil Stabilized Roads
Soil Stabilized Roads
Highway Maintenence
Highway Maintenence
Highway Drainage
Highway Drainage
Hill Roads
Hill Roads
Road Side Development
Road Side Development
Highway Economics and Finance
Highway Economics and Finance
Topics
This Chapter highway-drainage consists of the following topics
Guest